Skip to main content

Re: “Bruce Power gets reprieve over delays” published in the Toronto Star, August 14, 2012

August 11, 2012
The Editors
The Toronto Star
1 Yonge St.
Toronto, Ontario
Dear Sir/Madam,
Re: "Bruce Power gets reprieve over delays" Surely the delays in completing the Bruce Nuclear refurbishment project arising from errors in the drawings provided to Bruce Power by one of its suppliers are a matter to be resolved between the company and that supplier. There is no reason why Ontario electricity ratepayers should end up having to pay additional tens of millions of dollars for power they do not need as a result these errors.
Yours sincerely,
Mark S. Winfield, Ph.D. Associate Professor